CHART CAPACITY 10.0 t 10.0 t 8.7 t 7.2 t DAF ≤ 1.3 FLOOR DAF 1.5 DAF 1.8
Offshore crane load charts · dynamic derating

Where chart capacity goes when the sea moves — and how to keep the peak load near the floor.

Crane Load Chart

A crane load chart specifies the maximum safe working load (SWL) a crane can lift at different radii, boom lengths and angles. Offshore, the available chart capacity must be checked against dynamic loading because the hook, payload, deck and sea surface can all move relative to each other.

The dynamic load factor (ψ), often discussed together with DAF, is the multiplier applied to the static payload or crane chart capacity. A factor of 1.5 means the crane and rigging must withstand 50% more load than the static weight alone.

Where the extra load comes from

The largest capacity reductions usually come from relative velocity and sudden tension changes:

  • Lift-off from a supply vessel or barge – the crane hook and the cargo deck can move in opposite directions. If the hook rises while the deck or container drops, the sling can go from slack to fully loaded almost instantly. That snap load can exceed the static payload by a wide margin.
  • Splash-zone crossings – buoyancy, drag, added mass and wave particle velocity change quickly as the payload passes through the free surface. The result is a varying hook load and a higher dynamic factor.
  • Crane and wire elasticity – the crane, wire, slings and payload behave like a spring-mass system, so fast motion or poor timing can amplify peak tension.
  • Lift-off, landing and snagging – short events can dominate the maximum hook load even when the average sea state looks acceptable.

The dynamic load factor captures these effects in a single number applied to the crane load chart.

How to calculate relative velocity?

For deck lifts, classification rules commonly estimate relative velocity as:

v_r =\frac{1}{2}v_L + \sqrt{v_c^2+v_d^2}

Where v_r is the relative velocity, v_L is the crane lifting velocity, v_c is the crane-tip vertical velocity from vessel motion, and v_d is the deck or payload vertical velocity from wave motion.

We estimate v_c and v_d from vessel response data, measured motion, metocean data or time-domain simulation. When data is limited, conservative rule-based values can be used.

How to calculate dynamic factor and allowed payload?

For a conventional crane and rigging system, a dynamic factor can be estimated from relative velocity, stiffness and payload mass:

\psi =1 + \frac{v_r}{g} \sqrt{\frac{k}{m}}

Where v_r is the relative velocity, g is acceleration of gravity, k is the effective crane and wire stiffness, and m is the payload mass.

\psi is then used to derate the crane chart. Many offshore checks also apply a minimum dynamic factor, commonly 1.3 depending on rule set and lift category, so a calculated value below the minimum does not increase the chart capacity.

As an example, assume a crane has 10 t chart capacity for a deck lift and the applicable minimum dynamic factor is 1.3. What is the allowed overboard payload if the calculated dynamic factor is 1.2 or 1.8?

For 1.2, the minimum factor still controls, so the allowed payload remains 10 t. For 1.8, the allowed payload becomes:
m = 10 \cdot \frac{1.3}{1.8} = 7.2\ \text{t}

By reducing snap loads with shock absorption, or hook-to-payload relative motion with heave compensation, the lift can often be brought closer to the minimum dynamic factor instead of forcing a large chart derating.

Worked example: from velocities to allowed payload

The two formulas above chain into one derating calculation. Illustrative deck lift: hoisting at vL = 0.5 m/s, crane-tip vertical velocity vc = 0.6 m/s, supply-vessel deck velocity vd = 0.8 m/s, payload 10 t, effective crane-and-wire stiffness 400 kN/m (illustrative), chart cell 10 t, minimum factor 1.30.

  1. Relative velocity. vr = ½ vL + √(vc² + vd²) = 0.25 + √(0.36 + 0.64) = 1.25 m/s
  2. Dynamic factor. √(k/m) = √(400 000 / 10 000) ≈ 6.3 s−1, so ψ = 1 + (1.25 / 9.81) × 6.3 ≈ 1.8
  3. Allowed payload. ψ = 1.8 exceeds the 1.30 floor, so the chart cell derates: 10 × 1.30 / 1.8 = 7.2 t — a 28% capacity loss from relative motion alone.

Cut the relative velocity — a shock absorber for the single snap at pick-up, heave compensation for repeated wave-cycle motion — and ψ falls back toward the floor, recovering the same chart cell toward its full 10 t. Values are illustrative; the design factor for a real lift comes from analysis.

Illustrative load-chart effect

The example below shows the same crane chart capacity checked with different dynamic factors. It is a simplified calculation example, not a certified POLARIS load chart.

Example chart capacity10 tat one selected radius
Minimum dynamic factor1.30used as the reference floor
Controlled case 10.0 t
DAF 1.5 8.7 t
DAF 1.8 7.2 t

Calculation: allowed payload = chart capacity x 1.30 / dynamic factor. If a POLARIS crane shock absorber keeps the peak load near the minimum factor, the same chart cell can remain much closer to full capacity.

Allowed payload versus calculated dynamic factor for a 10 tonne chart cell with a 1.30 minimum factor: full capacity until the floor, hyperbolic derating beyond it, with the recoverable band shaded
Figure 1 — The example above as a continuous curve: allowed payload = 10 t × 1.30/ψ once ψ exceeds the floor. Keeping the peak load near the floor — shock absorption for a single snap event, heave compensation for repeated wave-cycle motion — keeps the chart cell near full capacity. Simplified example, not a certified load chart.

How to reduce load-chart derating

The practical question is not only what the dynamic factor is, but what causes it. Different load cases need different equipment.

  • Snap loads and deck pick-up: use a POLARIS crane shock absorber. The absorber adds controlled stroke and damping between crane and payload, so a single velocity mismatch — deck pick-up, snap, overload — is absorbed before it becomes peak hook load. It needs time to reset between events; where slack–snap cycles repeat through the wave zone, heave compensation is the right tool.
  • Splash-zone crossings and subsea lifts: use passive heave compensation to reduce hook-to-payload relative motion. RIGEL and CYGNUS cover simpler passive cases; ANTARES is used for complicated or multi-step subsea lifts with changing buoyancy.
  • Topside active heave compensation: use active heave compensation where residual motion must be minimized. In practice it is reserved for the narrow band of cases where the performance justifies the cost and complexity; for most load-chart cases an adaptive-passive compensator such as ANTARES closes much of the gap without external power.
  • Operational controls: use controlled hoisting speed, plan soft lift-off, avoid re-contact, avoid resonant sea states and use suitable weather windows. Equipment reduces the peak load, but the lift procedure still sets the starting conditions.

For a first-pass product check, use the heave compensator selection guide. For a full review, send the crane radius, SWL, lift speed, payload, sea state, wave period and lift sequence.

Standards and classification

Crane load charts for offshore operations are governed by DNV-ST-0378, DNV-RP-N202, API 2C and EN 13852. Norwegian Dynamics products are designed and classed according to DNV-ST-0378 where applicable.

Crane load charts — frequently asked

What is a crane load chart?
The table of maximum safe working load (SWL) a crane can lift at each radius, boom length and angle. Offshore, the chart value is the start of the check, not the end — dynamic loading must be applied on top.
Why are offshore crane load charts derated?
Because hook, payload, deck and sea surface move relative to each other. Snap loads at lift-off, splash-zone force changes and spring-mass amplification in the crane and wire all raise the peak hook load above the static weight, and the chart must absorb that through a dynamic factor.
What dynamic factor should I use?
Estimate it from relative velocity, effective stiffness and payload mass — and check the applicable rule set: many offshore checks apply a minimum factor, commonly around 1.3 depending on rules and lift category. A calculated value below the floor does not add capacity back.
How is allowed payload calculated?
Once the calculated factor ψ exceeds the floor: allowed payload = chart capacity × floor / ψ. A 10 t cell with a 1.3 floor still allows 10 t at ψ = 1.2, but only 8.7 t at 1.5 and 7.2 t at 1.8.
How do I get capacity back?
Reduce the peak, not the paperwork: a POLARIS crane shock absorber caps single snap events at deck pick-up; passive heave compensation cuts repeated hook-to-payload motion through the wave zone; and procedure — hoisting speed, soft lift-off, weather windows — sets the starting conditions. The mechanics behind the factor are on the DAF page.

Related resources

Working on a lift that needs this?

If load-chart derating is limiting the lift, send the crane and load case. We can separate snap-load, transfer-lift and splash-zone cases and suggest the practical next step.