Crane Shock Absorption
Screen the energy. Then verify the peak.
Passing the energy screen is one result.
The example compares the event demand with a simplified energy allowance. The actual transient peak still needs a separate verification.
What the event brings.
Relative engagement speed of approximately 3.13 m/s corresponds to approximately 0.500 m of equivalent free-fall/run distance.
What this screen allows.
For the declared assumptions, μ × η × S × (ψallow − 1) gives 0.540 m. This is not the physical stroke of the absorber.
Effective mass equals reference mass · physical stroke S = 4 m · usable-stroke fraction μ = 0.9 · energy factor η = 0.5 · allowed DAF ψallow = 1.3.
Required physical stroke from this screen: 0.50 ÷ [0.9 × 0.5 × (1.3 − 1)] ≈ 3.70 m. This example uses 4 m.
50 cm is below 54 cm. That does not establish that the transient peak stays below the allowed DAF of 1.3. The configured force–stroke response and coupled crane, wire, rigging and payload system must verify the actual peak.
Read the energy equations and revised calculation ↓Revised worked example and assumptions
Worked screening example: from relative velocity to stroke
- The event. Use an illustrative equivalent free-fall/run distance of 50 cm. This corresponds to a relative engagement speed of approximately 3.13 m/s.
- The stated assumptions. Let meff = mref, physical stroke S = 4 m, usable-stroke fraction μ = 0.9, energy factor η = 0.5 and allowed DAF ψallow = 1.3. These are example inputs, not transferable design values.
- The screen. Required physical stroke is about 3.70 m. Using 4 m gives hcap = μ η S (ψallow − 1) = 54 cm. Since 50 cm ≤ 54 cm, the example passes the energy screen. A transient check must still verify the actual peak and working-stroke margin.
The chart in the chart-assumptions section is a separate illustrative screen and uses the assumptions stated in its caption.
Do not read the chart as the worked example.
The original chart and worked example use different energy factors. Keep their assumptions attached to their results.
With μ = 0.9, S = 4 m, equal effective/reference mass and allowed DAF 1.3, the example gives a 54 cm equivalent allowance.
The chart uses μ = 0.9, equal effective/reference mass and g = 9.81 m/s². It varies physical stroke and allowed DAF to plot maximum relative engagement speed.
Neither factor is a universal product value. Use the case-specific usable-stroke fraction and verified force–stroke response. A plotted curve is an illustrative screen, not an equipment performance certificate.
Keep three checks in the selection.
Reference and demand
Define effective moving mass, relative engagement speed or equivalent event distance, allowed peak and the static load used as its DAF reference.
Transient response
Verify the configured force–stroke curve, system stiffness and preload, actual peak and the margin within usable travel.
Repeated duty
Check recurrence, reset time, thermal duty, environment, orientation and the nominated project/class basis.
Use the equipment configuration and project event to establish the assessment. See the inputs to send with a case →
