Riser Tensioning Systems
A riser tensioner holds a drilling riser in tension while the rig heaves around it. How much tension a riser needs, how much stroke and gas the tensioner needs, how wireline and direct-acting tensioners differ, and where a backup tensioner fits.
- A riser tensioner pulls up on the top of a marine drilling riser with a nearly constant force while the floating rig heaves. The riser hangs from the rig instead of standing on the well in compression, and the rig’s motion changes the riser’s tension only a little.
- API RP 16Q sets the minimum tension: the riser’s submerged weight less its buoyancy, plus the mud column’s weight above that of the seawater, with allowances for tolerances, a failed tensioner and friction. For the illustrative 1,500 m riser below with 1.5 SG mud that is about 420 t; at 3,000 m with 1.8 SG mud, about 1,100 t.
- Deepwater drilling units carry about 1,400 to 1,800 t (3,000 to 4,000 kips) of tensioner capacity, most often as 16 wire lines of 250 kips in eight dual wireline units, sometimes as six direct-acting cylinders, with about 15 m (50 ft) of travel.
- The gas volume sets how much the tension changes over the stroke: holding it within ±5 % takes a gas volume about 14 times the volume the stroke sweeps, and more when the stroke is fast.
- SIRIUS, our general-purpose tensioner family in development, can serve as a backup riser tensioner. It is planned from 5 to 5,000 t, with 1 to 12 m of stroke.
A floating drilling unit reaches the well through the marine drilling riser: a string of large-diameter steel pipe from below the drill floor down to the blowout preventer (BOP) on the seabed, carrying the drilling mud back up. The riser is too long and too heavy to stand on the BOP, so it hangs from the rig. The rig moves several metres over each wave cycle, and the pull has to stay nearly constant while it does. That is the tensioner’s job.
What a riser tensioner does
The top of the riser is a telescopic joint. Its inner barrel hangs from the rig under the drill floor and slides inside the outer barrel, which is the top of the riser. The tensioners attach to the tension ring on the outer barrel and carry the riser from there (Figure 1). As the rig heaves, the inner barrel slides and the tensioners stroke, while the riser below stays where it is.
Each tensioner is a hydraulic cylinder working against high-pressure gas. As the rig rises, the tensioner gives out stroke, pushes oil into its gas bottles and compresses the gas, so the tension rises a little. As the rig comes down, the gas pushes the oil back and the tension falls a little. The gas is the spring, and its volume decides how little the tension changes.
How much tension a riser needs
The riser has to be in tension along its whole length, or it can buckle. The tension at the top also keeps the angles at its flex joints small in current and when the rig drifts off the well. API RP 16Q sets the minimum with a balance at the tension ring, which it calls the slip ring:
Here W_s is the riser’s submerged weight and B_n the net lift of its buoyancy modules. The factors f_{wt} \ge 1.05 and f_{bt} \le 0.96 allow for weight tolerance and for buoyancy lost to compression and water absorption. A_i is the riser’s internal area, including its choke, kill and auxiliary lines, and d_m H_m and d_w H_w are the pressures of the mud column inside and the seawater column outside at the bottom of the riser.
The tensioners have to deliver more than that, because some of them can fail at once and a little is lost on the way to the ring:
with N tensioner lines or cylinders, n of them that can fail suddenly, and R_f, usually 0.90 to 0.95, for the fleet angle (how far the wire leans from vertical) and friction.
Worked example: a 1,500 m riser
- The inputs. Illustrative round numbers: 1,500 m of riser with a submerged weight of 900 t and 800 t of buoyancy lift, and A_i = 0.22\ \text{m}^2 for the bore and its lines. The mud is 1.50 SG against 1.025 for seawater, with both columns taken as 1,500 m. Twelve tensioner lines, of which one dual unit (two lines) can fail suddenly, and R_f = 0.95.
- At the tension ring. In tonnes, with the densities in t/m³, the weight term is 900 \cdot 1.05 = 945, the buoyancy term 800 \cdot 0.96 = 768 and the mud term 0.22 \cdot 1{,}500 \cdot (1.50 - 1.025) \approx 157, soT_{\text{SR,min}} = 945 - 768 + 157 \approx 334\ \text{t}
- The tensioner setting.T_{\min} = 334 \cdot \frac{12}{0.95 \cdot 10} \approx 422\ \text{t}That is about 4.1 MN, or 930 kips.
The buoyancy carries most of the steel, and the tolerance factors alone add about 80 t: 5 % on 900 t and 4 % off 800 t. Water depth and mud weight drive the rest. The same riser in 3,000 m of water with 1.8 SG mud needs about 1,100 t. Deepwater drilling units carry about 1,400 to 1,800 t of tensioner capacity to cover that minimum, the rise in tension over the stroke, and the extra tension that current and offset call for.
A real stack-up takes the weights from the riser joints’ data sheets and checks the effective tension along the whole riser, not only at the top. The top of the band is limited too, by the riser, the telescopic joint and tension ring, and the wellhead and conductor.
Stroke and gas volume
The stroke has to cover the rig’s heave at the riser, the set-down as the rig drifts off the well, the tide and the riser’s own stretch, with margin at both ends so the tensioner never bottoms out. Deepwater units have about 15 m (50 ft) of travel.
How much the tension changes over that stroke depends on the gas. With a gas volume V_0 at mid-stroke and a piston area A, a stroke x from mid-stroke that compresses the gas gives
where \kappa runs from 1.0 for slow, isothermal compression to about 1.4 for fast, adiabatic compression of an ideal gas. At the 100 to 200 bar a tensioner works at, real nitrogen is stiffer still, so fast strokes need more gas. The larger the gas volume against the volume the stroke sweeps, the flatter the curve (Figure 2). Holding the tension within ±5 % over the full stroke, for example, takes a gas volume about 14 times the swept volume, which is why tensioner systems carry banks of large gas bottles.
The same gas spring gives the riser and its tensioners a vertical natural period, which is checked against the wave periods of the operation. It matters most when the riser is disconnected and hangs off the tensioners, with nothing at the bottom to hold it.
Wireline and direct-acting tensioners
| Wireline tensioners | Direct-acting tensioners | |
|---|---|---|
| How the force reaches the riser | A wire rope from each cylinder’s sheaves runs over an idler sheave and down to the tension ring | The cylinders connect the drill-floor structure straight to the tension ring, with no wire |
| Stroke | The sheaves multiply the cylinder’s stroke, typically four times, so a short cylinder gives about 15 m of wire travel | The cylinder’s stroke is the riser’s travel, so the cylinders are long: about 15 m of stroke |
| Units | Twelve to sixteen wire lines of up to about 250 kips (113 t) each, usually grouped in dual units, in pairs on opposite sides to cancel side loads | Typically six cylinders around the riser |
| What wears | The wire ropes, which bend over the sheaves every wave cycle; sheaves and bearings | Rod seals and bearings; no ropes to maintain |
| Where used | Most deepwater drillships, including those delivered in 2022 and 2023, and most older rigs | Some semi-submersibles, including harsh-environment units |
Tensioner ropes
On a wireline system the ropes are what wears. Current units run lines of up to about 250 kips each. Every wave cycle bends the same few metres of rope over the sheaves, and salt air corrodes it, so rigs move the rope along on a schedule to spread the wear (slip and cut), inspect it, and replace it at the end of its life. The rope is specified to API Spec 9A, and its care and use follow API RP 9B. The idler sheaves are placed to keep the fleet angle small, which puts more of the rope tension into lifting the riser and makes the rope last longer.
Production risers
Top-tensioned production risers on tension-leg platforms and spars are held the same way, by hydro-pneumatic tensioners, or on some spars by buoyancy cans. There the tension is set for the life of the field rather than for a drilling campaign.
Design cases the tensioner must cover
- A failed tensioner. The factor N/(N - n) makes the remaining tensioners hold the minimum tension if one fails, or a dual unit, depending on how the system is split. On a direct-acting system a failed cylinder can also pull down on the tension ring, and that load is added to the minimum.
- Recoil after an emergency disconnect. When the lower marine riser package (LMRP) disconnects from the BOP in an emergency, the tensioners are still pulling with hundreds of tonnes on a riser that has lost its bottom connection, and the mud starts to drain out of it. The tension has to lift the LMRP clear of the BOP without it falling back onto the stack, but the riser must not shoot up into the rig, slacken the tensioner wires or collapse the telescopic joint. An anti-recoil system throttles the flow between the gas bottles and the cylinders, and a recoil analysis sets the tension and anti-recoil settings for each mud weight.
- Stroke margin. Heave, set-down, tide and stretch must fit inside the stroke, with margin at both ends, in every sea state the rig stays connected in. If the rig loses position, the stroke left is one of the limits on how early the disconnect has to start.
- The upper tension limit. Heavy mud raises the minimum towards what the riser, the tension ring, the wellhead and the tensioners themselves can take, and the rise in tension over the stroke has to stay under that limit too.
Backup tensioning and SIRIUS
A tensioner can go out of service for a seal failure, a rope change or maintenance. With one unit out, the others carry its share and the allowance for the next failure shrinks, which can force a lower mud weight or tighter operating limits until the unit is back. A backup tensioner takes the missing unit’s share while the primary is restored.
For scale, a backup that stands in for one dual wireline unit carries about 230 t, the load of two 250-kip lines.
SIRIUS, our general-purpose tensioner family in development, can serve as that backup: topside units with manually set damping, planned from 5 to 5,000 t with 1 to 12 m of stroke, for backup riser tensioning, workover and other constant-tension duties. The hardware behind SIRIUS is not new: our team has delivered long-stroke tensioners before, including a 500 t drilling tensioner with 8 m of stroke.
Riser tensioners and lift heave compensators are the same kind of machine, a cylinder working against a gas spring, judged in different ways. A tensioner is judged by how constant its tension stays over the stroke, and it runs for weeks. A lift compensator is judged by how little of the vessel’s motion reaches the load, over one lift. For compensation on a workover string or coiled tubing run from a crane, see coiled-tubing heave compensation.
Sources and assumptions
- The minimum-tension method is API RP 16Q: f_{wt} at least 1.05 unless the joints are weighed, f_{bt} at most 0.96 unless the buoyancy is weighed under pressure, and R_f usually 0.90 to 0.95.
- The worked example uses illustrative round numbers, not a riser design. Both fluid columns are taken as the water depth, which leaves out the air gap.
- Installed capacity and travel come from published rig specification sheets. Deepwater drillships delivered from 2011 to 2023 carry 3,200 to 4,000 kips on 16 wire lines of up to 250 kips, with 12.5 ft cylinders and 50 ft of wire travel. Two harsh-environment semi-submersibles carry six direct-acting cylinders of about 530 kips each, with 50 ft of stroke. A deepwater riser design study uses six direct-acting tensioners with a 4,144 kip limit (Woo, Han and Kim, WIT Transactions on Engineering Sciences 105, 2016). 1 kip is 4.448 kN, or about 0.454 t.
- The recoil requirements follow the ABS Guidance Notes on Drilling Riser Analysis (2017).
- Figure 2 uses the polytropic law for an ideal gas with \kappa = 1.3 and leaves out real-gas behaviour, friction and oil compressibility.
- SIRIUS figures are design targets; SIRIUS is in development.
Frequently asked questions
What does a riser tensioner do?
It holds the marine drilling riser in a nearly constant upward tension while the floating rig heaves, so the riser hangs from the rig instead of standing on the well in compression. Hydraulic cylinders working against high-pressure gas stroke with the rig, and the large gas volume keeps the change in tension over the stroke small.
How much tension does a drilling riser need?
API RP 16Q sets the minimum: the riser’s submerged weight less its buoyancy, plus the mud column’s weight above that of the seawater, with tolerance factors, then scaled up for a failed tensioner and friction. An illustrative 1,500 m riser with 1.5 SG mud needs about 420 t; at 3,000 m with 1.8 SG mud, about 1,100 t. Deepwater drilling units carry about 1,400 to 1,800 t (3,000 to 4,000 kips) of tensioner capacity.
What is the difference between wireline and direct-acting riser tensioners?
Wireline tensioners act through wire rope: sheaves on each cylinder multiply its stroke, typically four times, and the rope runs over an idler sheave and down to the tension ring. Direct-acting tensioners connect their cylinders straight to the tension ring, with no wire, so their stroke equals the riser’s travel and the cylinders are long. Most deepwater drillships use wireline tensioners; direct-acting cylinders appear on some semi-submersibles.
How much stroke does a riser tensioner need?
Enough for the rig’s heave at the riser, the set-down as the rig drifts off the well, the tide and the riser’s stretch, with margin at both ends. Deepwater units have about 15 m (50 ft) of travel.
Why do riser tensioners need so much gas?
The gas is the spring, and its volume sets how much the tension changes over the stroke. Holding the tension within ±5 % over the full stroke takes a gas volume about 14 times the volume the stroke sweeps, and more when the stroke is fast.
What are riser tensioner ropes?
The wire ropes of a wireline tensioner, which carry the force from the cylinder’s sheaves over an idler sheave to the tension ring; current units run lines of up to about 250 kips each. Every wave cycle bends them over the sheaves, so rigs slip and cut them on a schedule to spread the wear, inspect them and replace them at the end of their life. The rope is specified to API Spec 9A, and its care and use follow API RP 9B.
What is riser recoil?
When the riser is disconnected from the BOP in an emergency, the tensioners are still pulling with the full riser tension on a riser that has lost its bottom connection. The tension has to lift the lower marine riser package clear of the BOP without it falling back onto the stack, and an anti-recoil system throttles the flow from the gas bottles so the riser does not shoot up into the rig. A recoil analysis sets that window for each mud weight.
What does Norwegian Dynamics offer for riser tensioning?
SIRIUS, our general-purpose tensioner family in development, can serve as a backup riser tensioner: topside units with manually set damping, planned from 5 to 5,000 t with 1 to 12 m of stroke, for backup riser tensioning, workover and other constant-tension duties.
Planning backup tensioning for a riser?
Send us:
- the water depth, the riser stack-up and the mud weights
- the rig’s tensioner system and the unit a backup has to cover
- the stroke and the sea states the rig stays connected in
- how long the backup has to hold
We’ll review the case against the SIRIUS design targets and tell you what a backup unit would need to carry.
Send your riser case →