
Weather Windows and Operational Limits
The conditions must hold for the time the operation needs.
An envelope, a window and a campaign result.
Each answers a different question. Moving from one to the next needs more project information.
Operating envelope
Which conditions satisfy the defined response criteria for the lift?
Required data and output
- Required project input
- Vessel, crane, payload, rigging, compensation system and lift phase
- Output
- Case-specific Hs/Tp operating envelope
Executable window
Do conditions remain acceptable for the complete required period?
Required data and output
- Required project input
- Site and season data, required continuous duration, forecast and alpha criteria
- Output
- Executable windows, including persistence
Waiting time & cost
What delay and cost follow from the planned activities and their windows?
Required data and output
- Required project input
- Mobilisation, sequence, downtime logic and contracted day rate
- Output
- Waiting days and cost distribution
Continuity determines which periods are usable.
Both rows meet the criterion in 8 of 12 intervals. This example requires four consecutive intervals.
Illustrative requirement: at least four uninterrupted intervals inside the criterion.
A / Fragmented availability
8 of 12 intervals inside the criterion
- ✓
- ✓
- ×
- ✓
- ✓
- ×
- ✓
- ✓
- ×
- ✓
- ✓
- ×
B / Longer continuous runs
8 of 12 intervals inside the criterion
- ✓
- ✓
- ✓
- ✓
- ×
- ×
- ✓
- ✓
- ✓
- ✓
- ×
- ×
This is an explanatory sequence, not a weather record or a project screen. An actual operation uses its declared reference period and all applicable criteria.
What changing the threshold does in this record.
NDBC 41002 · 12 February–24 March 2023 · continuous windows of at least 24 hours.
The thresholds are scenario inputs. The 1.5 m and 2.5 m cases are not generic uncompensated/compensated limits. A project operating envelope must come from its own analysis.
Basis and assumptions
The figure uses buoy observations from NOAA NDBC 41002 in the western Atlantic, covering 12 February to 24 March 2023. Windows are continuous runs of at least 24 h below the two illustrated Hs thresholds, counted with the same uptime engine used in a CONSTELLATION study. The 1.5 m and 2.5 m thresholds are scenario inputs, not generic operating limits and not outputs of a compensator design. This six-week screen is not an annual-availability study or a campaign forecast; those require the project site, season, duration, operating envelopes, forecast rules and contract assumptions. A site-specific operability screening supplies that basis.