Offshore Decommissioning Lifting: Weight, Cutting and Release

Removal lifts start with less certainty than installation lifts: an old weight record, an aged structure, and a load that changes hands as it is cut free. What the rules ask for, what the numbers show, and where a compensator or a shock absorber helps.

By Norwegian Dynamics Engineering · April 2026 · Updated September 2026 · 14 min read
Blender render of a corroded subsea structure, recovered from the seabed, being landed on a transport barge beside the vessel, with new lift points and shackles on the old frame.
In brief
  • OSPAR’s 2023 inventory lists 1,948 oil and gas installations in the North-East Atlantic, 1,144 of them subsea structures: 1,385 operational, 277 closed down or being dismantled, and 171 decommissioned. In UK waters alone, 173 assets are expected to cease production between 2026 and 2031.
  • A removal weight is less certain than an installation weight. Contingency factors run from 1.0 or 1.03 for an object weighed within ±3 % to between 1.05 and 1.2 for an estimate, depending on the document and on how the weight is known.
  • The release needs its own check. If the last support lets go while the crane holds only part of the weight, the rest moves to the hook at once and the rigging overshoots: undamped, by as much again. A load that still sits on its cut faces stays there until the crane lifts it off.
  • A compensator or a shock absorber changes the dynamics, not the weight. It softens the snap at lift-off and the landing on a barge, and a shock absorber caps a release it cannot prevent, within its stroke. The static weight and the lift points still have to be proven.

An installation lift starts from a new structure with a weighed or calculated weight, designed lift points and a planned sequence. A removal lift starts from whatever decades of service have left: modifications, marine growth, trapped water and corrosion, with records that may be incomplete. Then the load has to be cut free, and it changes hands from the structure to the crane.

Why a removal lift is harder than an installation lift

InstallationRemoval
WeightWeighed or calculated from fabrication recordsRecords plus decades of modifications, marine growth, trapped water and deposits
StructureNew, checked for the installation load caseAged, with corrosion and fatigue to find; members and connections checked for the removal load path
Lift pointsDesigned and verified for the liftReassessed, or new lift points engineered and welded on
RecordsCurrent design and lifting documentationRecovered and checked; gaps filled by inspection and analysis
SequenceSeafastening is cut on the barge and the load is lifted off its supportsThe load is cut out of the structure it has stood in, often with the crane already holding part of it

The scale of decommissioning

OSPAR’s 2023 inventory of the North-East Atlantic counts 1,948 oil and gas installations, 1,144 of them subsea structures. Of these, 1,385 were operational, 277 closed down or being dismantled, 171 decommissioned, and 10 left in place under derogations from OSPAR’s rule of full removal.

In the UK, the North Sea Transition Authority’s August 2026 update puts the cost of the remaining programme at £43.4 billion (2025 prices), about £21 billion of it by 2032. It expects 173 assets to cease production from 2026 to 2031, and counted 10 topsides and 8 substructures removed in 2025. Its benchmarks show the cost of large jacket and topsides removals, over 3,000 t, rising with global demand for heavy lift vessels. On the Norwegian shelf, Offshore Norge’s February 2026 outlook covers 31 assets with decommissioning planned from 2025 to 2034, 21 of them with a planned end of production in that period, and about 190,500 t of topsides and 107,500 t of jackets to remove.

Topsides come off in one of three ways, or a mix: piece small, cut up offshore and shipped in containers; reverse installation, module by module with a heavy lift vessel; or a single lift of the whole topsides. The largest single-lift vessel takes topsides of up to 60,000 t. Each method has its own lifts, and each lift has its own weight, cut sequence and load transfer.

The weight: what the rules ask for

A lift is designed on a weight multiplied by a contingency factor that grows with the uncertainty. The published factors depend on how the weight is known:

How the weight is knownContingency factorSource
Weighed, documented tolerance within ±3 %at most 1.03DNV-OS-H102 (2012), Sec.3 C103
Estimated, not weighedat least 1.1DNV-OS-H102 (2012), Sec.3 C106
Final weighed weightat least 1.03GL Noble Denton 0027/ND (Rev 9, 2010), 5.2
Estimate, ISO 19901-5 weight-control class Aat least 1.05GL Noble Denton 0027/ND, 5.2
Estimate, class B or Cat least 1.10GL Noble Denton 0027/ND, 5.2
Removal: from weighed within ±3 % to equipment without documented installation weights, or marine growth estimated from surveysminimums from 1.0 to 1.2DNV-RP-H102 (2004), Table 2-3

DNV-ST-N001 replaced these documents in 2016 (current edition December 2023, lifting in its Section 16), and DNV-RP-N102 replaced the removal practice. The project works to the factors of the edition it is contracted to; the older documents show how the factor follows the evidence.

For removal, DNV’s guidance lists what service adds: equipment and structural modifications, new piping and cables, concrete fillings, flooded members and tank residues, with marine growth taken from surveys and treated as a permanent load. It recommends weighing where possible, and warns that conservative factors alone are often not enough: the lift is also checked with extreme centre-of-gravity positions, the lowest possible weight and the highest feasible buoyancy. Water trapped in a subsea structure can raise the hook load considerably as it leaves the water, and perforating the structure first is one answer. A non-skirted structure lifted off a clay seabed needs extra force at least equal to its submerged weight to break free; see subsea retrieval.

Published close-out reports show topside weights that held up well, and far less marine growth reaching the yard than was estimated. A 23,500 t topsides removed in one lift in 2017 came out within 0.25 % of the weight recorded at the lift, and about 600 t (under 3 %) below the estimate in its decommissioning programme. Marine growth was estimated at 6 to 10 % of the jacket weight on three large North Sea jackets, but yards receive far less, because it falls off in cutting and lifting and dries out on the way. For the lift, plan on the estimate, not on what reaches the quay.

Cutting free: the release

DNV’s removal guidance asks for the cuts to be verified complete before the lift, sometimes by two independent methods, and for a structure that may not be stable once fully cut to be kept partly cut or secured. Its lifting standard, written for cutting seafastening before a lift-off, asks for the cut to leave no vertical restraint and for the crane operator to have live load readings to stop the lift if something is still attached. The removal guidance also asks for crane load monitoring accurate to better than ±5 %, with a contingency procedure for an overload reading. Among the cases a removal analysis considers is a random reaction force from an incomplete cut.

The dynamics depend on how the last support lets go (Figure 1). Where the final cut is made with the crane attached, the crane is preloaded and the supports carry the rest of the weight. If that support then lets go at once (a hanging or cantilevered member, a connection in tension, or a cut face the load can slide or drop off), the remainder moves to the hook suddenly, and the rigging overshoots the new static load, by as much again when undamped.

Cut through, still bearing: the load stays on the cut face until the crane lifts it offmodulecutcrane: 70 %Cut through, still bearing:the load stays on the cutface until the cranelifts it off
The last support lets go: the hook takes the rest at once, and the rigging overshootsmodulecutcrane: 70 %The last support lets go:the hook takes the restat once, and the riggingovershoots
With a shock absorber in line, it strokes near its setting instead of letting the load climbabsorbermodulecutcrane: 70 %With a shock absorberin line, it strokes nearits setting instead ofletting the load climb
Figure 1. Whether the final cut moves load to the hook depends on how the last support lets go. A load bearing on a cut face stays there; a support that lets go hands its share to the hook at once. Schematic, not to scale; the unit in panel 3 hangs in line: wire, top shackle, absorber, bottom shackle, slings.

In a simple model with 5 % damping, a crane preloaded to 90 % of the true weight, for example to an estimate that was 10 % light, briefly carries about 109 %; preloaded to 70 %, about 126 % (Figure 2). A load that sits on its cut faces does not drop: it stays there until the crane lifts it off, and the transfer becomes the lift-off described below. A shock absorber in the line strokes near its setting instead, as long as the setting sits above the heaviest credible weight and the unit has stroke left.

Hook load after the last support lets go, as a percentage of the true weight, over four seconds. Preloaded to 90 percent, the hook load overshoots to 109 percent. Preloaded to 70 percent, it overshoots to 126 percent. Preloaded to 70 percent with a shock absorber set at 110 percent in the line, it stops at 110 percent. All settle at 100 percent.60 %70 %80 %90 %100 %110 %120 %130 %140 %01234seconds after the last support lets gohook load, % of the true weightA preloaded to 90 %: peak 109 %B preloaded to 70 %: peak 126 %C as B, absorber set at 110 %: peak 110 %
Figure 2. What happens to the hook load if the last support lets go at once, in a simple model: the part of the weight still on the supports moves to the hook, and the rigging overshoots. Preloaded to 90 % of the true weight, the hook briefly carries 109 %; preloaded to 70 %, 126 %. An ideal shock absorber set at 110 % strokes about 0.08 m instead of letting the load climb past its setting. Rigging and crane with a 1 s natural period and 5 % damping; crane tip held still.

So where the last cut is made under load, the preload is brought as close to the true weight as the evidence allows, but not above the lowest credible weight, or the load jumps up when the cut goes through; the peak at release is part of the crane and rigging check. Many removals are cut ahead instead, with the load held by its own weight, friction at the cut faces and temporary restraints, so the release is the lift-off. A single lift in 2017 worked that way: the legs had been cut months before. The vessel took up nearly all of the 23,500 t topsides over about 1.5 hours of deballasting, then separated with a 15-second fast lift that gave 1.5 m of clearance above the cut legs. It is the same idea as a quick lift: take the load before the release, and clear fast after it.

Lift-off from a structure, landing on a barge

A crane vessel lifting from a fixed platform, or from a barge, lifts off a structure that moves differently from its crane tip. DNV-RP-N103 treats that lift-off as a snap load: the snap velocity is the hoisting speed plus the relative vertical velocity between the object and the crane tip, and the snap force grows with the square root of the hoisting system’s stiffness. After lift-off, the load can meet the barge deck again as the barge heaves, or the platform as the crane tip drops. At set-down on a barge, the deck can rise into the load, so the contact speed is the lowering speed plus the deck’s upward speed. Our transfer lifts article works through both.

Where a compensator or a shock absorber helps

NeedUnit
Cap a release or a snatch that cannot be ruled outPOLARIS (75 to 4,000 t): a shock absorber that holds the force near its valve setting while it strokes, and resets for the next lift
Soften the snap at lift-off and the set-down on a bargeRIGEL (55 to 1,000 t) or CYGNUS (12.5 to 10,000 t): a passive gas spring in line, charged on deck for the lift’s weight
Clear the structure or the barge fast after lift-offANTARES (30 to 4,000 t): adaptive passive, with a quick lift that retracts to pull the load clear
Pull a subsea structure out of the seabedA passive unit in line takes the vessel’s heave as stroke, so the winch sets a slow, steady pull; see subsea retrieval

None of them changes the static weight, proves a lift point or completes a cut. They are sized once the weight basis and the load path are established, from a model of the lift. CONSTELLATION models the release, the lift-off and the landing with and without the unit, and reports the peak loads, the stroke used and the clearance.

Sources and assumptions
  • Installation counts: OSPAR Inventory of Offshore Installations 2023 (open dataset), counted by status. OSPAR’s web page and its 2025 summary give different totals on other dates and scopes.
  • UK figures: North Sea Transition Authority, UKCS Decommissioning Cost and Performance Update 2026 (August 2026). Norwegian figures: Offshore Norge’s decommissioning outlook, February 2026, read from its slides.
  • Removal methods: the US Bureau of Safety and Environmental Enforcement, UK decommissioning programmes and Norwegian authorities describe the same three. The 60,000 t single-lift capacity is the vessel operator’s figure.
  • Weight factors: DNV-OS-H102 (January 2012), GL Noble Denton 0027/ND Rev 9 (2010), DNV-RP-H102 (April 2004), all superseded; DNV-ST-N001 (December 2023) and DNV-RP-N102 (2019, amended 2021) are current. Removal guidance on weight, trapped water, cutting, monitoring and soil: DNV-RP-H102; lift-off cutting: DNV-OS-H205 (April 2014); snap load and soil breakout: DNV-RP-H103 (April 2011) 4.7.5 and 6.4.2, now DNV-RP-N103.
  • Close-out figures: UK decommissioning close-out reports published on GOV.UK (2019 onward), and a 2011 industry study of marine growth on North Sea jackets.
  • Figure 1 is a schematic, not to scale. Figure 2 is a one-degree-of-freedom model: a module on rigging and crane with a 1 s natural period and 5 % damping, the last support removed at once, and the crane tip held still. Undamped, the overshoot equals the transferred load; at 5 % damping it is 0.85 times it. The peaks do not depend on the period; the timing and the absorber’s stroke do. The absorber is ideal: rigid below its setting, holding exactly its setting while it strokes (about 0.08 m here, about 0.3 m with a 2 s period), and locking when the module stops. Its setting is taken on the true weight; on a real lift it has to sit above the heaviest credible weight. A real unit’s force rises somewhat past its setting as the valve opens: in the pile-run case on our POLARIS page, the load below the unit peaked at about 19.3 MN on an 18.0 MN setting. A real release depends on the cut sequence, whether the load can drop at all, the structure’s own flexibility, friction at the cut faces and the vessel’s motion, and is modelled case by case.

Frequently asked questions

Why are decommissioning lifts riskier than installation lifts?

The weight is less certain after decades of modifications, marine growth and trapped water; the structure and its lift points have aged; and the load moves from the structure to the crane as it is cut free, which can overshoot the static load if a support lets go at once.

What weight contingency factor applies to a removal lift?

It depends on how the weight is known and on the document the project works to. DNV-OS-H102 (2012) set at most 1.03 for an object weighed within ±3 % and at least 1.1 for an estimate, and DNV’s 2004 removal practice set minimums from 1.0 to 1.2. The current DNV-ST-N001 and DNV-RP-N102 replaced both.

How is the weight verified before a removal lift?

By weighing where possible, and otherwise from construction and installation records plus the operator’s records of modifications, with surveys for marine growth. The lift is also checked for extreme centre-of-gravity positions, the lowest possible weight and the highest feasible buoyancy.

What happens to the hook load when the final cut goes through?

If the last support lets go at once, whatever part of the weight it still carried moves to the hook, and the rigging overshoots: undamped, by as much again. In a simple one-degree-of-freedom model with 5 % damping, a crane preloaded to 90 % of the true weight briefly carries about 109 %; preloaded to 70 %, about 126 %. A load that still sits on its cut faces stays there until the crane lifts it off. Where the cut is made under load, the preload is brought close to the true weight first.

What do heave compensators and shock absorbers add in decommissioning?

A shock absorber caps a release or a snatch near its setting, within its stroke; a passive compensator softens the snap at lift-off and the set-down on a barge; a quick lift clears the load fast after lift-off. None of them changes the static weight or proves a lift point.

Can the original lift points be reused for removal?

Only once their condition and capacity are verified for the removal load case. Otherwise new lift points are engineered and welded on, or another load path is found.

Planning lifts for a decommissioning campaign?

Send us:

  • the asset records, survey findings and the weight and centre-of-gravity basis
  • the lift points and the structural assessment
  • the cut and release sequence, the crane and rigging, and the vessel or barge

We’ll model the release, the lift-off and the landing in CONSTELLATION and recommend the compensator or shock absorber, if the lift needs one.

Send your lift case →

Related products

  • CYGNUS: Passive heave compensator
  • ANTARES: Adaptive passive heave compensator
  • RIGEL: Passive heave compensator
  • POLARIS: Crane shock absorber

Related reading